Stated forOperatorSiteMWResultSources
Sep 2026Cipher Mining / Cipher DigitalBarber Lake, Mitchell County168SlippedNo power date on recordstated · outcome
Jun 2026Cipher MiningStingray100SlippedNo power date on recordstated · outcome
Jun 2026DataBankRed Oak campus, Ellis County240SlippedNo power date on recordstated · outcome
Jun 2026STACK InfrastructureDFW02 South Dallas campus, Dallas County—SlippedNo power date on recordstated · outcome
Mar 2026Soluna HoldingsProject Kati 1, Willacy County83HeldPower Feb 2026stated · outcome
Dec 2025Cipher MiningBlack Pearl300HeldPower Jun 2025stated · outcome
Dec 2025CrusoeAbilene, Taylor County200HeldPower Sep 2025stated · outcome
Dec 2025GlobalWafersGlobalWafers America 300mm silicon wafer fab, Grayson County—HeldPower May 2025stated · outcome

All 46 dates

Building in Texas?

Send the site, the megawatts and the date you were given.