Capability 04
Deadline Clock
The Batch Zero dates, each carried to the approved rule text or ERCOT market notice that sets it. Miss one and the load comes out of the study.
- PUCT approved the Batch Zero packageDoneJun 18, 2026
- ILLE submission deadlineClosedJul 10, 2026
- TSP/DSP qualification packages due to ERCOTClosedJul 24, 2026
- QSA prerequisites for early-2027 energizationClosedAug 1, 2026
- ERCOT classification resultsScheduledAug 7, 2026
- Deficiency cure deadlineScheduledAug 31, 2026
- Batch Zero study report & MW allocationScheduledApr 9, 2027